The 183MW Isimba Hydro Power Project (HPP) is located 4km downstream of Simba Falls on the River Nile, approximately 50km downstream of the Source of the Nile. The project site is about 21km from Kayunga Town as the nearest town and about 65km from Jinja Town. The Power Station will be installed with four vertical Kaplan turbine generator units with a capacity of 45.8MW per unit, thereby providing a combined installed capacity of 183.2MW.

Key Dates

  • 05th October 2013: Construction works launched by President Yoweri .K. Museveni
  • 30th April 2015 :  Project Commencement Date

 

Implementing Agency

Uganda Electricity Generation Company Limited

Contractor

China International Water & Electric Corporation

Project Duration

40 months

Project Cost

567.7 USD Million

Government of Uganda - 15%

EXIM Bank(Loan china) - 85%

Funding Agency

The People’s Republic of China

Implementation Engineer

Engineering, Procurement & Consulting Engineer

SMEC International Pty. Ltd

Capacity

183 MW

Expected Completion Date

August 2018

Project Status

Civil Works

Concrete works approx. 99.8%, gravity dams 1 & 2 completed, spillways 1 & 2 completed, tailrace apron completed, wall cladding of power house building using masonry blocks ongoing, roofing works (roof truss and roof covering) completed, By the end of August 2017, Concreting of Unit 1, 2, 3 and 4 were at elevations 1045.45, 1045.45, 1043.71 and 1043.71 respectively RED material placement of clay, coarse filter, fine filter and rock fill ongoing, LED foundation treatment completed. Approximately 75% of the civil works have been certified as completed.

Electromechanical Works

EoT Crane installed and tested, upstream and downstream gantry cranes, cooling units delivered to site. Approximately 67% of electromechanical works have been certified as completed.

Hydro mechanical works

Embedment works on all units and spillways completed, draft tubes, draft tube cones, lower spillway radial gates, draft tube gates, trash racks and hydraulic gates and hydraulic hoists installation completed. Approximately 67% of the hydro mechanical works have been certified as completed.

Transmission line

124 out of 145 towers have been erected. 135 out of 145 foundations have been constructed. 4 towers were erected during the month of August 2017.Transimission line stands at 64% of certified completed works.

Percentage of All works completed

Total overall completed work is at 70.4%